Building Committee Approves Bid Release, Budget Items

The Millis School Building Committee voted unanimously to release early trade bid packages for the middle school renovation project. Vertex managing director Jeff introduced new project executive Ted Gentry and reported bids go live October 16 with a November 6 due date.

Townbrief reporting ·

School panel backs added radon vent piping

The School Building Committee voted unanimously by roll call to adopt the consultant's radon plan for the Millis school project. The plan calls for four passive riser vents in the new area and 10 in the existing building, up from three and four. Power wiring and fans were deferred.

Townbrief reporting ·

Building Committee OKs 30% design submission to MSBA

The School Building Committee approved sending the 30 percent design development package to the MSBA. The project management team reported that Fontaine's estimate came to $98.1 million, matching PM&C's total and landing below the overall budget, about $145,000 under.

Townbrief reporting ·

Get Millis's town government news by email, free. One briefing each morning.

Share this story

Email Text Facebook X

Anyone can open a shared story. Members' stories show the free part and a sign-up line to people who are not members.